The Hook Lab / Tracker / North America / United States / Amazon Hilliard Scioto Darby Creek Road campus
Updated 2026-11-25
Tracker · United States · PJM · OH
Amazon Hilliard Scioto Darby Creek Road campus
Amazon Data Services · 4186 Scioto Darby Creek Road, Hilliard, OH
Planning approvedchanged 2025-09-22
—requested
—offered
—energised
—waiting: no filing date on record
highconfidence · 2 sources
- Market
- United States · North America
- Grid
- PJM · PJM
- Place
- 4186 Scioto Darby Creek Road, Hilliard, OH
- Network
- —
- Planning approved
- 2025-09-22
- First reported by
- hilliardohio.gov · approved
- Dates it gives
- campus approved by city 2022
fuel cells approved by Ohio Power Siting Board 2025-09-22
fuel cell construction from 2026-01, operation 2027-09
Who is on it
- Owner
- Ohio Power Company · hilliardohio.gov
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2025-09-22
stagePlanning approvedconfirmed
- hilliardohio.gov primary
The Ohio Power Siting Board approved this fuel cell project on Sept. 22, 2025.
- compute-atlas.com press
OPSB approved (2025-09-22) a 72.9 MW behind-the-meter solid oxide fuel cell facility (228 Bloom Energy units) at 4186 Scioto Darby Creek Rd, owned and operated by Ohio Power Company and serving Amazon only.
- hilliardohio.gov primary
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.