The Hook Lab / Tracker / North America / United States / Amazon Becker data centre Updated 2026-11-25
Tracker · United States · MISO · MN

Amazon Becker data centre

Amazon · Becker, MN

Pausedstage not on recordchanged 2025-05-23
—requested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 2 sources
Market
United States · North America
Grid
MISO · MISO
Place
Becker, MN
Network
—
First reported by
Star Tribune · cancelled
Dates it gives
abandoned 2025-05

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2025-05-23date: document dateon or before
    conditionPausedconfirmed
    • mprnews.org press
      Amazon is pausing plans to build a large data center in the central Minnesota city of Becker.
    • fox9.com press
      Amazon suspended plans to build a data center in Becker, Minnesota.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.