The Hook Lab / Tracker / North America / United States / Amazon Ashton Avenue data centre
Updated 2026-11-25
Tracker · United States · PJM · VA
Amazon Ashton Avenue data centre
Amazon Web Services · Ashton Avenue, Manassas area, Prince William County, VA
Contestedplanning approvalstage not on recordchanged 2024-10
—requested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
- Market
- United States · North America
- Grid
- PJM · PJM
- Place
- Ashton Avenue, Manassas area, Prince William County, VA
- Network
- —
- First reported by
- DCD · paused
- Dates it gives
- shelved 2024-10
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2024-10
conditionContested1 sourceplanning approval
- DCD press
In October 2024, county supervisors shelved an proposal to build three Amazon data centers on 52 acres along Ashton Avenue. The proposal was previously recommended for denial by the county planning commission, citing concerns regarding noise, impacts on local wildlife, and the site's proximity to residential areas.
- DCD press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.