The Hook Lab / Tracker / Oceania / Australia / Zerra DC Campbellfield Updated 2026-11-25
Tracker · Australia · NEM · VIC

Zerra DC Campbellfield

Zerra DC · Campbellfield, VIC

Planning lodgedchanged 2026-04
336 MWrequested
—offered
—energised
8 mowaiting since first filing
highconfidence · 2 sources
Market
Australia · Oceania
Grid
NEM · National Electricity Market
Place
Campbellfield, VIC
Network
—
Planning lodged
2026-04
First reported by
hume.vic.gov.au · contested
Dates it gives
Lodged with DTP 2026-04 (DFP)
public notice 2026-07
EPA Victoria formal objection reported 2026-08-26
Hume council called for rejection 2026-08-26
Stage 1 targeted Q2 2028

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2026-04
    stagePlanning lodgedconfirmed
    • Zerra DC primary
      The planning application was submitted through the Department of Transport and Planning’s Development Facilitation Program in [April] 2026 and was placed on public notice between 14 and 28 July 2026.
    • Information Age (ACS) press
      Singapore-headquartered tech firm Zerra DC has lodged a planning application directly with the Victoria Minister for Planning Sonya Kilkenny for the data centre campus on the site of a former Ford car factory in Campbellfield in the state’s north.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.

Report an error