Vantage Data Centres · Newport

Operating since 2009
148 MWplanned
—live
1source
Market
United Kingdom · Europe
Grid
GB · Great Britain (NESO)
Place
Newport
Owner
Vantage Data Centres
Opened
2009
Dates the source gives
opened 2009 as Next Generation Data
acquired by Vantage in July 2020 (also given as April 2020)
fifth building planning consultation 2021
third building still to come
Source
research.senedd.wales

From its first public source so far, linked above, with the dates that source gives. Each step found in registers, filings and the press is added here with its source and the quote it rests on.