The Hook Lab / Tracker / Asia / South Korea / Tilon Jeju net-zero data centre Updated 2026-11-25
Tracker · South Korea · KEPCO · Jeju

Tilon Jeju net-zero data centre

Tilon · Jeju, Jeju

Announcedchanged 2024-08-09
40 MWrequested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
Market
South Korea · Asia
Grid
KEPCO · KEPCO
Place
Jeju, Jeju
Network
—
Announced
2024-08-09
First reported by
ihalla.com · planned
Dates it gives
MOU signed 2024-08-09

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2024-08-09
    stageAnnounced1 source
    • ihalla.com press
      [한라일보] 국내 소프트웨어 기업인 (주)틸론이 전력의 100%를 재생에너지로 쓰는 '넷제로(Net-Zero, 탄소중립) 인터넷 데이터센터'를 제주에 짓기로 했다.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.

Report an error