The Hook Lab / Tracker / Oceania / Australia / Stockland Macquarie Park Stage 1 Updated 2026-11-25
Tracker · Australia · NEM · NSW

Stockland Macquarie Park Stage 1

Stockland · 11-17 Khartoum Road and 33-39 Talavera Road, Macquarie Park, NSW

Planning lodgedchanged 2020-05-29
—requested
—offered
—energised
≥ 78 mowaiting since first filing
highconfidence · 2 sources
Market
Australia · Oceania
Grid
NEM · National Electricity Market
Place
11-17 Khartoum Road and 33-39 Talavera Road, Macquarie Park, NSW
Network
—
Planning lodged
2020-05-29
First reported by
NSW planning portal · under construction
Dates it gives
approved 2021-05-28

Who is on it

Developer
Stockland Trust Management Limited · majorprojects.planningportal.nsw.gov.au
Developer
Stockland Development Pty Ltd · majorprojects.planningportal.nsw.gov.au

Timeline

20202022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2020-05-29date: document dateon or before
    stagePlanning lodgedconfirmed
    • NSW planning portal primary
      This Scoping Report has been prepared to seek Secretary’s Environmental Assessment Requirements (SEARs) for the Project.
    • NSW planning portal primary
      since submitting the EIS to DPIE

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.

Report an error