Updated 2026-11-25
Tracker · Australia · NEM · NSW
Starwood Doma Minchinbury
Starwood Capital / Doma Infrastructure Group · Minchinbury, NSW
Planning approvedchanged 2025-11-13
62 MWrequested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 3 sources
- Market
- Australia · Oceania
- Grid
- NEM · National Electricity Market
- Place
- Minchinbury, NSW
- Network
- —
- Planning approved
- 2025-11-13
- First reported by
- Mingtiandi · approved
- Dates it gives
- Development approval by 2025-11
construction start early 2026
in service early 2028
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2025-11-13date: document dateon or before
stagePlanning approvedconfirmed
- PR Newswire press
Development Approval has been secured for the Minchinbury site, which will support 62MW of IT load within an 90MVA power envelope.
- FNArena press
Development Approval has been secured for the Minchinbury site, which will support 62MW of IT load within an 90MVA power envelope.
- Mingtiandi press
Positioned next to the Eastern Creek data centre cluster, the Minchinbury site has received development approval and is scheduled to begin construction in early 2026 and enter service in early 2028 as a hyperscale-ready facility for artificial intelligence workloads.
- PR Newswire press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.