Jeonnam Province / Haenam-gun / KEPCO / Jeonnam Development Corp · Solaseado Guseong District, Haenam-gun, Jeollanam-do

Under constructionchanged 2026-08-04
1,000 MWrequested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
Market
South Korea · Asia
Grid
KEPCO · KEPCO
Place
Solaseado Guseong District, Haenam-gun, Jeollanam-do
Network
—
Construction started
2026-08-04
First reported by
DCD · application lodged
Dates it gives
2023-08 MOTIE business agreement
phase 1 (5 buildings + 300 MW substation) by 2027
phase 3 by 2037

Who is on it

Operator
Samsung SDS · thelec.net

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-08-04date: document dateon or before
    stageUnder construction1 source
    • thelec.net press
      South Korea's Ministry of Science and ICT (MSIT) held a groundbreaking ceremony on Aug. 3 for the National AI Computing Center at the Solaseado Data Center Park in Haenam, located in the Gwangju–South Jeolla Integrated Special City, marking the official start of construction.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.