The Hook Lab / Tracker / Asia / Japan / SC Zeus OSA1
Updated 2026-11-25
Tracker · Japan · KANSAI · Osaka
SC Zeus OSA1
SC Capital Partners / Tokyo Tatemono · 1-7-18 Nanko-kita, Suminoe-ku, Osaka, Osaka
Under constructionchanged 2026-01-29
—requested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 3 sources
- Market
- Japan · Asia
- Grid
- KANSAI · Kansai Transmission and Distribution
- Place
- 1-7-18 Nanko-kita, Suminoe-ku, Osaka, Osaka
- Network
- —
- Connection offered
- 2026-01-29
- Construction started
- 2025-12
- First reported by
- kansai-sanpo.com · under construction
- Dates it gives
- construction start 2025-12-01
completion planned 2028-01-31
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2026-01-29date: document dateon or before
stageConnection offered1 source
- kansai-sanpo.com press
同プロジェクトは2フェーズで構築され、最終的に総ITロード70MWを提供する計画で、関西電力からの100MWの受電枠により供給基盤を確保しています。
- kansai-sanpo.com press
-
2025-12
stageUnder constructionconfirmed
- kansai-sanpo.com press
シンガポールの投資ファンド「SCキャピタル・パートナーズ」は、2025年12月、日本第1号プロジェクトとなるデータセンター「Zeus OSA1」を大阪市内で着工したと発表しました。
- sccpasia.com press
has commenced construction of a new best-in-class data centre in Osaka with 100MW of allocated power. The first phase would have a total investment of approximately USD 600 million and has secured the necessary building permits in advance of the groundbreaking ceremony held on 3 December 2025.
- kansai-sanpo.com press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.