The Hook Lab / Tracker / Asia / Japan / NTT West Hakata Data Center
Updated 2026-11-25
Tracker · Japan · KYUSHU · Fukuoka
NTT West Hakata Data Center
NTT West · Hakata-ku, Fukuoka, Fukuoka
Announcedchanged 2026-06-23
5 MWrequested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
- Market
- Japan · Asia
- Grid
- KYUSHU · Kyushu Electric Power T&D
- Place
- Hakata-ku, Fukuoka, Fukuoka
- Network
- —
- Announced
- 2026-06-23
- First reported by
- businessnetwork.jp · no status given
- Dates it gives
- announced 2026-06-23
completion scheduled FY2029
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2026-06-23
stageAnnounced1 source
- note.com press
On June 23, 2026, NTT West announced that it would build a new next-generation AI-compatible "Hakata Data Center" in Hakata Ward, Fukuoka City.
- note.com press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.