NEXTDC SC2 Sunshine Coast
NEXTDC · Maroochydore (10 South Sea Islander Way), QLD
Planning approvedchanged 2025-06
6 MWrequested
—offered
—energised
20 mowaiting since first filing
mediumconfidence · 2 sources
- Market
- Australia · Oceania
- Grid
- NEM · National Electricity Market
- Place
- Maroochydore (10 South Sea Islander Way), QLD
- Network
- —
- Planning lodged
- 2025-03-18
- Planning approved
- 2025-06
- Planning lodged → approved
- 2 mo
- First reported by
- sunshinecoastnews.com.au · under construction
- Dates it gives
- approved 2025-06
expected online 2027-01 to 2027-06
Who is on it
- Architect
- Architectus · yourneighbourhood.com.au
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2025-06
stagePlanning approved1 source
- sunshinecoastnews.com.au press
Economic Development Queensland approved SC2 in June 2025.
- sunshinecoastnews.com.au press
-
2025-03-18
stagePlanning lodged1 source
- yourneighbourhood.com.au press
A development application has been submitted for a Research and Technology Industry use (Data Centre) for NEXTDC, located at 10 South Sea Islander Way, Maroochydore.
- yourneighbourhood.com.au press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.