The Hook Lab / Tracker / Oceania / Australia / NEXTDC S4 Data Centre Phase 2
Updated 2026-11-25
Tracker · Australia · NEM · NSW
NEXTDC S4 Data Centre Phase 2
NEXTDC · 6 Johnston Crescent, Horsley Park, NSW
Planning lodgedchanged 2023-10-16
—requested
—offered
—energised
37 mowaiting since first filing
mediumconfidence · 1 source
- Market
- Australia · Oceania
- Grid
- NEM · National Electricity Market
- Place
- 6 Johnston Crescent, Horsley Park, NSW
- Network
- —
- Planning lodged
- 2023-10-16
- First reported by
- NSW planning portal · application lodged
- Dates it gives
- exhibition 2026-10-13 to 2026-11-10
Who is on it
- Developer
- NEXTDC · majorprojects.planningportal.nsw.gov.au
Timeline
2022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2023-10-16
stagePlanning lodgedconfirmed
- NSW planning portal primary
This letter has been prepared by Urbis Pty Ltd (Urbis) on behalf of NEXTDC (Proponent) in support of a request for industry specific Secretary Environmental Assessment requirements (SEARs) for a proposed data centre development at 3-5 Johnston Crescent, Horsley Park.
- NSW planning portal primary
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.