The Hook Lab / Tracker / Oceania / Australia / NEXTDC M4
Updated 2026-11-25
Tracker · Australia · NEM · VIC
NEXTDC M4
NEXTDC · Port Melbourne, VIC
Planning approvedchanged 2026-01-21
162 MWrequested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
- Market
- Australia · Oceania
- Grid
- NEM · National Electricity Market
- Place
- Port Melbourne, VIC
- Network
- —
- Planning approved
- 2026-01-21
- First reported by
- The Urban Developer · approved
- Dates it gives
- Land bought 2023
plans public 2025-01
Victorian Government approval ~2026-01 (75-day fast-track)
construction est. 18 months after approval
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2026-01-21date: document dateon or before
stagePlanning approved1 source
- The Urban Developer press
NextDC has received development approval from the Victorian Government for its M4 technology campus at Fishermans Bend Innovation Precinct in Port Melbourne.
- The Urban Developer press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.