The Hook Lab / Tracker / Asia / South Korea / National AI Computing Center Updated 2026-11-25
Tracker · South Korea · KEPCO · Jeollanam-do

National AI Computing Center

Korea AI Computing Center SPC · Solaseado, Sani-myeon, Haenam-gun, Jeollanam-do

Under constructionchanged 2026-08-03
40 MWrequested
—offered
—energised
4 mowaiting since first filing
mediumconfidence · 2 sources
Market
South Korea · Asia
Grid
KEPCO · KEPCO
Place
Solaseado, Sani-myeon, Haenam-gun, Jeollanam-do
Network
—
Connection applied
2026-08-03
Construction started
2026-08-03
First reported by
zdnet.co.kr · under construction
Dates it gives
2026-03 Haenam confirmed
2026-06 SPC formed
2026-08-03 groundbreaking
2028 completion

Who is on it

Developer
Samsung SDS · zdnet.co.kr

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-08-03date: document dateon or before
    stageConnection applied1 source
    • zdnet.co.kr press
      코아크는 한국전력에 전기 사용 신청을 완료했으며 용수 인입 관로 공사와 건물 신축, 고성능 AI 서버 운영을 위한 설비 공사를 추진한다.
  2. 2026-08-03
    stageUnder construction1 source
    • zdnet.co.kr press
      배경훈 부총리 겸 과학기술정보통신부 장관은 3일 전남광주통합특별시 해남군 솔라시도 데이터센터 파크 부지에서 열린 국가AI컴퓨팅센터 착공식에서 "AI 컴퓨팅센터는 단순한 건물이나 인프라 환경이 아니라 전 세계에 토큰을 생산하는 '토큰 팩토리'"라며 "대한민국이 AI를 세계에 수출하는 국가로 자리 잡게 될 것"이라고 강조했다.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.