Microsoft Station Road campus
Microsoft · Seven Hills, NSW
Planning lodgedchanged 2021-06-07
—requested
—offered
—energised
66 mowaiting since first filing
highconfidence · 2 sources
- Market
- Australia · Oceania
- Grid
- NEM · National Electricity Market
- Place
- Seven Hills, NSW
- Network
- —
- Planning lodged
- 2021-06-07
- First reported by
- DCD · under construction
- Dates it gives
- Site bought 2021-04
SSD-33781208 expansion approved 2022-12-16
Building 1 est. 2023-07
Building 2 started 2023-06, due late 2024
Who is on it
- Builder
- FDC Construction · datacenterdynamics.com
- Planning consultant
- Patch Planning · majorprojects.planningportal.nsw.gov.au
Timeline
20202022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2021-06-07
stagePlanning lodgedconfirmed
- NSW planning portal primary
The report has been prepared following consultation with the Department of Planning, Industry and Environment (DPIE ) and accompanie s a request for the Secretary’s Environmental Assessment Requirements (SEARs).
- NSW planning portal primary
The subject State significant development (SSD) application seeks approval for the Station Road Data Centre Expansion.
- NSW planning portal primary
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.