The Hook Lab / Tracker / Oceania / Australia / Microsoft Lane Cove North Updated 2026-11-25
Tracker · Australia · NEM · NSW

Microsoft Lane Cove North

Microsoft · Lane Cove North, NSW

Planning lodgedContestedplanning approvalchanged 2022-11-25
—requested
—offered
—energised
≥ 69 mowaiting since first filing
highconfidence · 4 sources
Market
Australia · Oceania
Grid
NEM · National Electricity Market
Place
Lane Cove North, NSW
Network
—
Planning lodged
2021-02-16
First reported by
DCD · cancelled
Dates it gives
Site bought ~A$63m
council deferred demolition approval 2022-04
Microsoft confirmed drop 2023-02

Who is on it

Developer
Microsoft · datacenterdynamics.com
Planning consultant
Willowtree Planning · planningportal.nsw.gov.au

Timeline

20202022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2022-11-25
    conditionContested1 sourceplanning approval
    • NSW planning portal primary
      I strongly object to the applicant’s submission in Appendix 27 of the SSD to change the requirement and exclude Clause 4.3 of LCLEP2009.
  2. ≤ 2021-02-16date: document dateon or before
    stagePlanning lodgedconfirmed
    • NSW planning portal primary
      request for the Planning Secretary's environmental assessment requirements (SEARS) for the construction of a 24-hour operation data centre at 706 Mowbray Road, Lane Cove North.
    • NSW planning portal primary
      1 28.05.2021 SSDA Submission
    • NSW planning portal primary
      Application No: SSD-13475973

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.