The Hook Lab / Tracker / Europe / Portugal / Merlin Edged Lisbon region data centre Updated 2026-11-25
Tracker · Portugal · PT

Merlin Edged Lisbon region data centre

Merlin Edged · Lisbon

Under construction
1,300 MWplanned
—live
1source
Market
Portugal · Europe
Grid
PT · Portugal (REN)
Place
Lisbon
Owner
Merlin Edged
Dates the source gives
80 MW under construction with entry expected by end of 2027
Source
jornaleconomico.sapo.pt

From its first public source so far, linked above, with the dates that source gives. Each step found in registers, filings and the press is added here with its source and the quote it rests on.

Report an error