The Hook Lab / Tracker / Asia / Japan / Kuwana data centre development site
Updated 2026-11-25
Tracker · Japan · Mie
Kuwana data centre development site
Kuwana City · northern Kuwana, Mie
Connection appliedchanged 2026-07-10
120 MWrequested
—offered
—energised
5 mowaiting since first filing
mediumconfidence · 2 sources
- Market
- Japan · Asia
- Grid
- not settled yet
- Place
- northern Kuwana, Mie
- Network
- —
- Announced
- 2026-07-10
- Connection applied
- 2026-07-10
- First reported by
- nikkei.com · planned
- Dates it gives
- power supply about four years after a construction contract
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
- ≤ 2026-07-10date: document dateon or before
-
≤ 2026-07-10date: document dateon or before
stageAnnounced1 source
- nikkei.com press
約23万平方メートルとバンテリンドームナゴヤ(名古屋市)約5個分の広さを持つこの土地を、桑名市はDC向けの開発用地として事業者を募っている。
- nikkei.com press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.