The Hook Lab / Tracker / Asia / South Korea / KT Cloud Gasan AI Data Center
Updated 2026-11-25
Tracker · South Korea · KEPCO · Seoul
KT Cloud Gasan AI Data Center
KT Cloud · Gasan, Geumcheon-gu, Seoul, Seoul
Energisedchanged 2025-11-05
—requested
—offered
—energised
—closed
mediumconfidence · 2 sources
- Market
- South Korea · Asia
- Grid
- KEPCO · KEPCO
- Place
- Gasan, Geumcheon-gu, Seoul, Seoul
- Network
- —
- Construction started
- 2022-07-07
- First power
- 2025-11-05
- First reported by
- ajunews.com · operating · opened 2025
- Dates it gives
- opened 2025-11-05
Who is on it
- Owner
- KT Cloud · ajunews.com
- Financier
- Shinhan Investment · koreajoongangdaily.com
Timeline
2022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
- 2025-11-05
-
≤ 2022-07-07date: document dateon or before
stageUnder construction1 source
- koreajoongangdaily.com press
Construction on a 26-megawatt data center in Geumcheon District, southern Seoul, has begun, KT Cloud announced Thursday.
- koreajoongangdaily.com press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.