The Hook Lab / Tracker / Asia / South Korea / Koramco-DCI Ansan Siwha AI Data Center
Updated 2026-11-25
Tracker · South Korea · KEPCO · Gyeonggi-do
Koramco-DCI Ansan Siwha AI Data Center
Koramco AMC · Seonggok-dong, Ansan, Gyeonggi-do
Under constructionchanged 2026-06-08
40 MWrequested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 4 sources
- Market
- South Korea · Asia
- Grid
- KEPCO · KEPCO
- Place
- Seonggok-dong, Ansan, Gyeonggi-do
- Network
- —
- Announced
- 2026-06-08
- Construction started
- 2026-05-28
- First reported by
- Asia Economy · under construction
- Dates it gives
- 2025-08 partnership
2026-06-08 groundbreaking
Who is on it
- Builder
- Hyundai Engineering & Construction · mk.co.kr
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2026-06-08
stageAnnounced1 source
- mk.co.kr press
announced on the 8th that they will start developing data centers in the Sihwa National Industrial Complex in Ansan, Gyeonggi-do.
- mk.co.kr press
-
2026-05-28
stageUnder constructionconfirmed
- en.sedaily.com press
Officials from Koramco Asset Management and DCI Data Center hold a groundbreaking ceremony for the Ansan Sihwa AI Data Center on the 28th of last month.
- Asia Economy press
On June 8, Koramco Asset Management announced that it has begun construction of a 40MW artificial intelligence (AI) data center within the Siwha National Industrial Complex in Ansan, Gyeonggi Province, in partnership with DCI Data Center, the Asia-Pacific data center operator under Brookfield.
- mk.co.kr press
The two companies held a groundbreaking ceremony for the Ansan Sihwa AI Data Center Development Project at the Seonggok-dong business site in Danwon-gu, Ansan-si, Gyeonggi-do.
- en.sedaily.com press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.