The Hook Lab / Tracker / Asia / Japan / Kasumigaseki Capital Zama data centre
Updated 2026-11-25
Tracker · Japan · TEPCO · Kanagawa
Kasumigaseki Capital Zama data centre
Kasumigaseki Capital / SC Zeus Data Centers · Zama, Kanagawa
Connection offeredchanged 2026-08-28
42 MWrequested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 2 sources
- Market
- Japan · Asia
- Grid
- TEPCO · TEPCO Power Grid
- Place
- Zama, Kanagawa
- Network
- —
- Announced
- 2026-08-28
- Connection offered
- 2026-08-28
- First reported by
- voix.jp · connection offered
- Dates it gives
- project launch announced 2026-08-28
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2026-08-28date: document dateon or before
stageConnection offered1 source
- voix.jp press
最大の特徴は、42MW規模の特別高圧受電(7000ボルトを超える高い電圧で電気を受けること)に関する電気使用申込契約を締結済みである点だ。
- voix.jp press
- ≤ 2026-08-28date: document dateon or before
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.