The Hook Lab / Tracker / Asia / South Korea / Gumi Advanced AI Data Centre Cluster
Updated 2026-11-25
Tracker · South Korea · KEPCO · Gyeongsangbuk-do
Gumi Advanced AI Data Centre Cluster
Quantum XI consortium · Gumi Hi-Tech Valley (National Industrial Complex 5), Gumi, Gyeongsangbuk-do
Announcedchanged 2024-12-13
1,300 MWrequested
—offered
—energised
—waiting: no filing date on record
highconfidence · 4 sources
- Market
- South Korea · Asia
- Grid
- KEPCO · KEPCO
- Place
- Gumi Hi-Tech Valley (National Industrial Complex 5), Gumi, Gyeongsangbuk-do
- Network
- —
- Announced
- 2024-12-13
- First reported by
- twig24.com · no status given
- Dates it gives
- MOU 2025-12-18
phase 1 start targeted 2026-Q1, completion 2027-H1
full cluster 2029
Who is on it
- Developer
- Lohod Partners · gb.go.kr
- Financier
- NH Investment & Securities · gb.go.kr
- Financier
- KORAMCO Asset Management · gumi.go.kr
- Financier
- KB Securities · gb.go.kr
- Developer
- Rohod Partners · view.asiae.co.kr
- Developer
- Nscale · view.asiae.co.kr
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2024-12-13
stageAnnouncedconfirmed
- gumi.go.kr primary
구미시는 13일 시청에서 이철우 경북도지사, 김장호 구미시장, 박교상 구미시의회 의장, ㈜구미하이테크에너지 김병선 대표이사, ㈜코람코자산운용 박형석 대표이사 등이 참석한 가운데 구미하이테크밸리(5산단 1단계)에 AI데이터센터와 수소연료전지발전소를 결합한 첨단 복합시설 건설을 위한 투자양해각서(MOU)를 체결했다고 밝혔다.
- gb.go.kr primary
경상북도와 구미시는 18일 경북도청 경북시대에서 퀀텀일레븐(Quantum XI) 컨소시엄과 함께 ‘구미 첨단 AI 데이터센터 클러스터’ 조성을 위해 4조 5천억원 규모의 업무협약을 체결했다.
- Asia Economy press
On December 18 at 2:00 p.m., North Gyeongsang Province and the City of Gumi held a memorandum of understanding (MOU) ceremony with the Quantum XI consortium to establish the "Gumi Advanced AI Data Center Cluster" within the Gumi High-Tech Valley (National 5 Industrial Complex), at the North Gyeongsang Provincial Government office.
- gb.go.kr primary
경상북도와 구미시는 18일 경북도청 경북시대에서 퀀텀일레븐(Quantum XI) 컨소시엄과 함께 ‘구미 첨단 AI 데이터센터 클러스터’ 조성을 위해 4조 5천억원 규모의 업무협약을 체결했다.
- gumi.go.kr primary
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.