Google Kronstorf data centre
Google · Kronstorf, Upper Austria
Application lodged
500 MWplanned
—live
1source
- Market
- Austria · Europe
- Grid
- AT · Austria (APG)
- Place
- Kronstorf, Upper Austria
- Owner
- Dates the source gives
- groundbreaking April 2026
permit procedure expected to be concluded by mid-2027 at the latest
construction of the larger phase expected to start after that (next year, 2027) - Source