The Hook Lab / Tracker / Oceania / Australia / Goodman Project Pluto
Updated 2026-11-25
Tracker · Australia · NEM · NSW
Goodman Project Pluto
Goodman · Guildford West, NSW
Planning approvedchanged 2026-07-23
68 MWrequested
—offered
—energised
32 mowaiting since first filing
mediumconfidence · 3 sources
- Market
- Australia · Oceania
- Grid
- NEM · National Electricity Market
- Place
- Guildford West, NSW
- Network
- —
- Planning lodged
- 2024-04-08
- Planning approved
- 2026-07-23
- Planning lodged → approved
- 27 mo
- First reported by
- W.Media · approved
- Dates it gives
- Earlier 126 MW application withdrawn 2024-04
SSD approved by 2026-07 (A$1.11bn)
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2026-07-23
stagePlanning approvedconfirmed
- certifiedstrategic.com press
The NSW Department of Planning, Housing and Infrastructure approved Goodman's Project Pluto data centre at 132 McCredie Road, Guildford West on 23 July 2026.
- dcpulse.com press
Approved / Permitted (State Significant Development Approval)
- certifiedstrategic.com press
-
2024-04-08
stagePlanning lodged1 source
- DCD press
Goodman has filed with New South Wales to develop a data center campus at 132 McCredie Road in Sydney's Guildford West.
- DCD press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.