The Hook Lab / Tracker / Oceania / Australia / Goodman Project Duke Data Centre
Updated 2026-11-25
Tracker · Australia · NEM · NSW
Goodman Project Duke Data Centre
Goodman Group · 2 and 10-22 Kent Road, Mascot, NSW
Planning lodgedchanged 2024-05-16
—requested
—offered
—energised
30 mowaiting since first filing
highconfidence · 3 sources
- Market
- Australia · Oceania
- Grid
- NEM · National Electricity Market
- Place
- 2 and 10-22 Kent Road, Mascot, NSW
- Network
- —
- Planning lodged
- 2024-05-16
- First reported by
- NSW planning portal · approved
- Dates it gives
- approved 2025-12-22
Who is on it
- Developer
- Goodman Property Services (Aust) Pty Ltd · majorprojects.planningportal.nsw.gov.au
- Developer
- Goodman Property Services (Aust.) Pty Ltd · majorprojects.planningportal.nsw.gov.au
- Planning consultant
- Mecone Group Pty Limited · majorprojects.planningportal.nsw.gov.au
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2024-05-16
stagePlanning lodgedconfirmed
- NSW planning portal primary
We write on behalf of Goodman Property Services (Aust.) Pty Ltd (Goodman) to request the Department of Planning and Environment (DPE) to issue Secretary’s Environmental Assessment Requirements (SEARs) for a Data Centre at 2 & 10-22 Kent Road, Mascot (the site).
- NSW planning portal primary
This ESD Report has been prepared by Arup to support the application for SSD-71368959, the Project Duke Data Centre developed by Goodman Property Services (Aust) Pty Ltd.
- NSW planning portal primary
This Social Impact Assessment (SIA) report accompanies a detailed State Significant Development Application that seeks approval for a data centre and associated works in Mascot, NSW.
- NSW planning portal primary
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.