The Hook Lab / Tracker / Asia / Japan / GLP Akishima
Updated 2026-11-25
Tracker · Japan · TEPCO · Tokyo
GLP Akishima
GLP · Akishima, Tokyo
Contestedcommunity oppositionstage not on recordchanged 2024-07
295 MWrequested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
- Market
- Japan · Asia
- Grid
- TEPCO · TEPCO Power Grid
- Place
- Akishima, Tokyo
- Network
- —
- First reported by
- DCD · contested
- Dates it gives
- Construction planned from 2024-02
completion 2029
220+ residents opposed and planned arbitration 2024-07
still listed as planned 2026
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
- 2024-07
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.