The Hook Lab / Tracker / Oceania / Australia / Firmus Launceston AI Factory campus Updated 2026-11-25
Tracker · Australia · NEM · TAS

Firmus Launceston AI Factory campus

Firmus Technologies · St Leonards, Launceston, TAS

Planning approvedchanged 2026-09-14
—requested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
Market
Australia · Oceania
Grid
NEM · National Electricity Market
Place
St Leonards, Launceston, TAS
Network
—
Planning approved
2026-09-14
First reported by
W.Media · approved
Dates it gives
Announced 2025-07
City of Launceston planning permit 2025-09
Aurora Energy 3-yr retail agreement 2026-03-25 with ramp Aug–Nov 2026
first 42 MW hall topped out 2026-10-07

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-09-14date: document dateon or before
    stagePlanning approved1 source
    • DCD press
      Project Southgate is approved by Launceston City Council

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.