The Hook Lab / Tracker / Oceania / Australia / Firmus Bell Bay AI Factory
Updated 2026-11-25
Tracker · Australia · NEM · TAS
Firmus Bell Bay AI Factory
Firmus Technologies · Long Reach, Bell Bay (George Town), TAS
Planning approvedchanged 2026-08-25
288 MWrequested
—offered
—energised
3 mowaiting since first filing
mediumconfidence · 2 sources
- Market
- Australia · Oceania
- Grid
- NEM · National Electricity Market
- Place
- Long Reach, Bell Bay (George Town), TAS
- Network
- —
- Planning lodged
- 2026-08-21
- Planning approved
- 2026-08-25
- Planning lodged → approved
- 0 mo
- First reported by
- W.Media · approved
- Dates it gives
- George Town Council approved 6–1 on 2026-08-25 with 19 conditions
EPA decided no environmental assessment needed 2026-08
construction not started
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2026-08-25
stagePlanning approved1 source
- abc.net.au press
Six of seven present councillors voted to give the 288-megawatt development the go-ahead.
- abc.net.au press
-
≤ 2026-08-21date: document dateon or before
stagePlanning lodged1 source
- abc.net.au press
A visualisation of the Firmus site submitted as part of the planning application for Bell Bay.
- abc.net.au press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.