The Hook Lab / Tracker / Oceania / Australia / Firmus Bell Bay AI Factory Updated 2026-11-25
Tracker · Australia · NEM · TAS

Firmus Bell Bay AI Factory

Firmus Technologies · Long Reach, Bell Bay (George Town), TAS

Planning approvedchanged 2026-08-25
288 MWrequested
—offered
—energised
3 mowaiting since first filing
mediumconfidence · 2 sources
Market
Australia · Oceania
Grid
NEM · National Electricity Market
Place
Long Reach, Bell Bay (George Town), TAS
Network
—
Planning lodged
2026-08-21
Planning approved
2026-08-25
Planning lodged → approved
0 mo
First reported by
W.Media · approved
Dates it gives
George Town Council approved 6–1 on 2026-08-25 with 19 conditions
EPA decided no environmental assessment needed 2026-08
construction not started

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2026-08-25
    stagePlanning approved1 source
    • abc.net.au press
      Six of seven present councillors voted to give the 288-megawatt development the go-ahead.
  2. ≤ 2026-08-21date: document dateon or before
    stagePlanning lodged1 source
    • abc.net.au press
      A visualisation of the Firmus site submitted as part of the planning application for Bell Bay.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.