The Hook Lab / Tracker / Asia / Japan / ESR Ariake Data Centre
Updated 2026-11-25
Tracker · Japan · TEPCO · Tokyo
ESR Ariake Data Centre
ESR · Ariake, Koto-ku, Tokyo, Tokyo
Announcedchanged 2024-05-16
60 MWrequested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
- Market
- Japan · Asia
- Grid
- TEPCO · TEPCO Power Grid
- Place
- Ariake, Koto-ku, Tokyo, Tokyo
- Network
- —
- Announced
- 2024-05-16
- First reported by
- W.Media · no status given
- Dates it gives
- announced 2024-05
construction start planned 2026-Q2
completion planned 2028-Q4
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2024-05-16
stageAnnounced1 source
- DCD press
Logistics real estate firm ESR has announced plans to develop a 60MW data center in Central Tokyo, Japan.
- DCD press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.