The Hook Lab / Tracker / Asia / Japan / EdgeConneX Kyotanabe Updated 2026-11-25
Tracker · Japan · KANSAI · Kyoto

EdgeConneX Kyotanabe

EdgeConneX · Kyotanabe, Kyoto

Under constructionchanged 2026-03
200 MWrequested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
Market
Japan · Asia
Grid
KANSAI · Kansai Transmission and Distribution
Place
Kyotanabe, Kyoto
Network
—
Construction started
2026-03
First reported by
EdgeConneX · under construction
Dates it gives
Announced 2025-01-13 as >140 MW
groundbreaking 2026-03-17
first phase RFS Q1 2028

Who is on it

Developer
EdgeConneX · dcmarketinsights.com

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2026-03
    stageUnder construction1 source
    • dcmarketinsights.com press
      Started construction of its first Japan campus, a 200 MW AI-ready hyperscale campus on 130,000 sqm in Greater Osaka (ITM01 at the Kagoya Tatara Campus, Kyotanabe), with Kagoya Asset Management; first phase ready for service in Q1 2028.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.