The Hook Lab / Tracker / Oceania / Australia / DigiCo BNE3 Brisbane Airport
Updated 2026-11-25
Tracker · Australia · NEM · QLD
DigiCo BNE3 Brisbane Airport
DigiCo Infrastructure REIT · Brisbane Airport, Export Park (Cycas Lane, next to BNE2), QLD
Announcedchanged 2025-11-12
19.6 MWrequested
—offered
—energised
—waiting: no filing date on record
highconfidence · 2 sources
- Market
- Australia · Oceania
- Grid
- NEM · National Electricity Market
- Place
- Brisbane Airport, Export Park (Cycas Lane, next to BNE2), QLD
- Network
- —
- Announced
- 2025-11-12
- First reported by
- Data Center Map · no status given
- Dates it gives
- expected completion 2027
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2025-11-12date: document dateon or before
stageAnnouncedconfirmed
- announcements.asx.com.au primary
Brisbane 3 will be a 20MW greenfield development adjacent to our existing Brisbane sites. We are in discussions with Brisbane Airport Corporation to develop this site.
- announcements.asx.com.au primary
-
≤ 2025-08-18date: document dateon or before
milestoneRenamedconfirmed
- announcements.asx.com.au primary
Note BNE3 has been re named (previously BNE4 at time of PDS), given location is physically adjacent to BNE1 & BNE2.
- announcements.asx.com.au primary
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.