The Hook Lab / Tracker / Asia / Japan / DayOne Kodaira
Updated 2026-11-25
Tracker · Japan · TEPCO · Tokyo
DayOne Kodaira
DayOne · Kodaira, Tokyo
Under constructionchanged 2026-10-15
—requested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
- Market
- Japan · Asia
- Grid
- TEPCO · TEPCO Power Grid
- Place
- Kodaira, Tokyo
- Network
- —
- Construction started
- 2026-10-15
- First reported by
- Baxtel · no status given
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2026-10-15date: document dateon or before
stageUnder construction1 source
- DCD press
The company recently announced it broke ground on Phase I of the DayOne Kodaira Data Center in Tokyo.
- DCD press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.