The Hook Lab / Tracker / Europe / United Kingdom / CyrusOne Iver Heath data centre Updated 2026-11-25
Tracker · United Kingdom · GB

CyrusOne Iver Heath data centre

CyrusOne · Iver Heath

Approved
90 MWplanned
—live
1source
Market
United Kingdom · Europe
Grid
GB · Great Britain (NESO)
Place
Iver Heath
Owner
CyrusOne
Dates the source gives
construction start 2026
first power mid-2027
first output early 2028
Source
bucksfreepress.co.uk

From its first public source so far, linked above, with the dates that source gives. Each step found in registers, filings and the press is added here with its source and the quote it rests on.