The Hook Lab / Tracker / Europe / United Kingdom / Court Lane hyperscale data centre campus Updated 2026-11-25
Tracker · United Kingdom · GB

Court Lane hyperscale data centre campus

Corscale · Iver

Planned
140 MWplanned
—live
1source
Market
United Kingdom · Europe
Grid
GB · Great Britain (NESO)
Place
Iver
Owner
Corscale
Dates the source gives
enabling works start 1 July (2026)
practical completion late 2029
Source
industrialisedconstruction.co.uk

From its first public source so far, linked above, with the dates that source gives. Each step found in registers, filings and the press is added here with its source and the quote it rests on.