The Hook Lab / Tracker / Asia / South Korea / Changwon Yangdeok-dong AI data centre
Updated 2026-11-25
Tracker · South Korea · KEPCO · Gyeongsangnam-do
Changwon Yangdeok-dong AI data centre
Samgong Percent · Yangdeok-dong 974-15, Masanhoewon-gu, Changwon, Gyeongsangnam-do
Contestedcommunity oppositionstage not on recordchanged 2026-08-25
80 MWrequested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
- Market
- South Korea · Asia
- Grid
- KEPCO · KEPCO
- Place
- Yangdeok-dong 974-15, Masanhoewon-gu, Changwon, Gyeongsangnam-do
- Network
- —
- First reported by
- twig24.com · contested
- Dates it gives
- grid impact assessment 02-19 (year not stated)
city MOU reported 2026-08-20
investment planned by 2028
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2026-08-25
conditionContested1 sourcecommunity opposition
- twig24.com press
마산창원진해환경운동연합은 25일 기자회견을 열고 양덕동 대규모 데이터센터 건립 계획을 전면 백지화하라고 창원시에 촉구했다.
- twig24.com press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.