The Hook Lab / Tracker / Asia / South Korea / Changwon Yangdeok-dong AI data centre Updated 2026-11-25
Tracker · South Korea · KEPCO · Gyeongsangnam-do

Changwon Yangdeok-dong AI data centre

Samgong Percent · Yangdeok-dong 974-15, Masanhoewon-gu, Changwon, Gyeongsangnam-do

Contestedcommunity oppositionstage not on recordchanged 2026-08-25
80 MWrequested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
Market
South Korea · Asia
Grid
KEPCO · KEPCO
Place
Yangdeok-dong 974-15, Masanhoewon-gu, Changwon, Gyeongsangnam-do
Network
—
First reported by
twig24.com · contested
Dates it gives
grid impact assessment 02-19 (year not stated)
city MOU reported 2026-08-20
investment planned by 2028

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2026-08-25
    conditionContested1 sourcecommunity opposition
    • twig24.com press
      마산창원진해환경운동연합은 25일 기자회견을 열고 양덕동 대규모 데이터센터 건립 계획을 전면 백지화하라고 창원시에 촉구했다.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.

Report an error