The Hook Lab / Tracker / Oceania / Australia / CDC Marsden Park Campus Updated 2026-11-25
Tracker · Australia · NEM · NSW

CDC Marsden Park Campus

CDC Data Centres · Marsden Park, NSW

Planning lodgedchanged 2024-04-24
—requested
—offered
—energised
31 mowaiting since first filing
mediumconfidence · 1 source
Market
Australia · Oceania
Grid
NEM · National Electricity Market
Place
Marsden Park, NSW
Network
—
Planning lodged
2024-04-24
First reported by
W.Media · under construction
Dates it gives
Works commenced 2024-10-25
SSD approved 2025-11-28 (A$3.1bn)

Who is on it

Planning consultant
Mecone Group Pty Limited · majorprojects.planningportal.nsw.gov.au
Developer
Canberra Data Centres Pty Ltd · majorprojects.planningportal.nsw.gov.au
Planning consultant
Astrolabe Group · majorprojects.planningportal.nsw.gov.au
Planning consultant
Patch Planning · majorprojects.planningportal.nsw.gov.au

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2024-04-24
    stagePlanning lodgedconfirmed
    • NSW planning portal primary
      Early works DA (PAN-426243) lodged with Blacktown City Council to seek consent for tree removal, earthworks and remediation.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.