The Hook Lab / Tracker / Oceania / Australia / CDC Maddington Campus Updated 2026-11-25
Tracker · Australia · WEM · WA

CDC Maddington Campus

CDC Data Centres · Bickley Road industrial precinct, Maddington, WA

Planning lodgedchanged 2025-09-18
—requested
—offered
—energised
≥ 15 mowaiting since first filing
highconfidence · 2 sources
Market
Australia · Oceania
Grid
WEM · Wholesale Electricity Market (SWIS)
Place
Bickley Road industrial precinct, Maddington, WA
Network
—
Announced
2025-09-18
Planning lodged
2025-09-04
First reported by
CDC Data Centres · under construction
Dates it gives
announced 2025-08-13
development approval reported 2025-09-17
first building operational early 2027

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2025-09-18date: document dateon or before
    stageAnnouncedconfirmed
    • announcements.asx.com.au primary
      CDC has announced our Maddington campus in Perth, which will be the largest AI and advanced technology data centre campus in the region, expected to deliver 200MW+ of high-density capacity when complete.
  2. ≤ 2025-09-04date: document dateon or before
    stagePlanning lodgedconfirmed

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.