Announcedchanged 2026-09-23
192 MWrequested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
- Market
- Australia · Oceania
- Grid
- WEM · Wholesale Electricity Market (SWIS)
- Place
- 178-196 Bushmead Road, Hazelmere, WA
- Network
- —
- Announced
- 2026-09-23
- First reported by
- businessnews.com.au · no status given
- Dates it gives
- reported 2026-09-23
final public consultation session 2026-10
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2026-09-23date: document dateon or before
stageAnnounced1 source
- businessnews.com.au press
Critical digital infrastructure operator CDC Data Centres has unveiled plans to construct a 192-megawatt data centre in Hazelmere, marking its second planned development in WA.
- businessnews.com.au press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.