The Hook Lab / Tracker / Asia / South Korea / Busan Yeongdo AI Data Center
Updated 2026-11-25
Tracker · South Korea · KEPCO · Busan
Busan Yeongdo AI Data Center
Changhae Development · Former shipyard site, Namhang, Yeongdo-gu, Busan, Busan
Connection offeredchanged 2026-09-14
—requested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
- Market
- South Korea · Asia
- Grid
- KEPCO · KEPCO
- Place
- Former shipyard site, Namhang, Yeongdo-gu, Busan, Busan
- Network
- —
- Connection offered
- 2026-09-14
- First reported by
- Asia Economy · approved
- Dates it gives
- building permit 2022-12
MOU with POSCO E&C 2025-05
completion target end-2028
Who is on it
- Financier
- CCGI · mk.co.kr
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2026-09-14date: document dateon or before
stageConnection offered1 source
- DCD press
The data center will have five floors underground, and seven above ground, as has 80MW contracted with Korea Electric Power Corporation.
- DCD press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.