Busan Eco Delta Green Data Center
Busan Eco Delta Green Data Center PFV · Eco Delta City, Gangseo-gu, Busan, Busan
Connection offeredchanged 2026-08-11
300 MWrequested
—offered
—energised
—waiting: no filing date on record
highconfidence · 2 sources
- Market
- South Korea · Asia
- Grid
- KEPCO · KEPCO
- Place
- Eco Delta City, Gangseo-gu, Busan, Busan
- Network
- —
- Announced
- 2024-02-06
- Connection offered
- 2026-08-11
- First reported by
- breezeinflow.com · connection offered
- Dates it gives
- PFV announcement 2026-08-11
power supply from 2028-06-01
completion target 2028-H1
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2026-08-11
stageConnection offered1 source
- breezeinflow.com press
Busan Eco Delta Green Data Center PFV said on Aug. 11 that it had signed an electricity-use agreement with Korea Electric Power Corp.’s Busan-Ulsan headquarters for 300 megawatts of commercial supply, supported by a separately configured 300MW standby system.
- breezeinflow.com press
-
2024-02-06
stageAnnouncedconfirmed
- busan.go.kr primary
부산광역시는 지난 2월 6일 시청에서 데이터센터 전문기업인 (주)부산에코델타 그린데이터센터 PFV, Empyrion DC 컨소시엄, BEP&미래에셋 컨소시엄, (주)엘리스그룹 대표 등과 투자양해각서를 체결했다.
- busan.go.kr primary
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.