The Hook Lab / Tracker / Asia / South Korea / Busan Eco Delta Green Data Center Updated 2026-11-25
Tracker · South Korea · KEPCO · Busan

Busan Eco Delta Green Data Center

Busan Eco Delta Green Data Center PFV · Eco Delta City, Gangseo-gu, Busan, Busan

Connection offeredchanged 2026-08-11
300 MWrequested
—offered
—energised
—waiting: no filing date on record
highconfidence · 2 sources
Market
South Korea · Asia
Grid
KEPCO · KEPCO
Place
Eco Delta City, Gangseo-gu, Busan, Busan
Network
—
Announced
2024-02-06
Connection offered
2026-08-11
First reported by
breezeinflow.com · connection offered
Dates it gives
PFV announcement 2026-08-11
power supply from 2028-06-01
completion target 2028-H1

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2026-08-11
    stageConnection offered1 source
    • breezeinflow.com press
      Busan Eco Delta Green Data Center PFV said on Aug. 11 that it had signed an electricity-use agreement with Korea Electric Power Corp.’s Busan-Ulsan headquarters for 300 megawatts of commercial supply, supported by a separately configured 300MW standby system.
  2. 2024-02-06
    stageAnnouncedconfirmed
    • busan.go.kr primary
      부산광역시는 지난 2월 6일 시청에서 데이터센터 전문기업인 (주)부산에코델타 그린데이터센터 PFV, Empyrion DC 컨소시엄, BEP&미래에셋 컨소시엄, (주)엘리스그룹 대표 등과 투자양해각서를 체결했다.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.