The Hook Lab / Tracker / Asia / South Korea / Bosung Group Updated 2026-11-25
Tracker · South Korea · KEPCO · Jeollanam-do

Bosung Group

Bosung Group · Solaseado, Haenam-gun, Jeollanam-do

Announcedchanged 2026-09-14
200 MWrequested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
Market
South Korea · Asia
Grid
KEPCO · KEPCO
Place
Solaseado, Haenam-gun, Jeollanam-do
Network
—
Announced
2026-09-14
First reported by
Asia Economy · no status given
Dates it gives
2022-09-22 investment agreement
construction 2023-2030 planned

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-09-14date: document dateon or before
    stageAnnounced1 source
    • DCD press
      South Korean energy and construction firm Bosung Group is to build a new 200MW data center campus in SolaSeaDo, to the south of the country in Jeonnam Province.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.

Report an error