The Hook Lab / Tracker / North America / Canada / Beacon Heartland campus Updated 2026-11-25
Tracker · Canada · AESO · AB

Beacon Heartland campus

Beacon Data Centers · About 7 km east of Gibbons, Sturgeon County, Industrial Heartland, AB

Planned
800 MWplanned
—live
1source
Market
Canada · North America
Grid
AESO · Alberta (AESO)
Place
About 7 km east of Gibbons, Sturgeon County, Industrial Heartland, AB
Owner
Beacon Data Centers
Dates the source gives
Power plant construction targeted to start Q4 2026
plant running by late 2027
Beacon targeting fall 2027 for first operations
Source
thelogic.co

From its first public source so far, linked above, with the dates that source gives. Each step found in registers, filings and the press is added here with its source and the quote it rests on.