Aurora Energy Precinct AI data centre
1414 Degrees · North of Port Augusta, SA
Announcedchanged 2026-10-29
1,000 MWrequested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 2 sources
- Market
- Australia · Oceania
- Grid
- NEM · National Electricity Market
- Place
- North of Port Augusta, SA
- Network
- —
- Announced
- 2026-10-29
- First reported by
- pv-magazine-australia.com · no status given
- Dates it gives
- Non-binding HoA announced 2026-07-28
33 kV connection pathway announced 2026-07
definitive agreements pending
Who is on it
- Owner
- 1414 Degrees · pv-magazine-australia.com
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2026-10-29date: document dateon or before
stageAnnouncedconfirmed
- kalkinemedia.com press
has entered into a Heads of Agreement with an Australian data centre operator to develop up to 1 gigawatt of AI data centre infrastructure in stages at its Aurora Energy Precinct near Port Augusta, South Australia
- pv-magazine-australia.com press
1414 Degrees announced it has signed a Heads of Agreement with an Australian data centre operator to develop up to 1 GW of AI data centre infrastructure at its Aurora Energy Precinct in South Australia, anchored on Aurora’s firmed renewable generation and storage assets.
- kalkinemedia.com press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.