The Hook Lab / Tracker / Asia / South Korea / Ansan OUR Data Centre
Updated 2026-11-25
Tracker · South Korea · KEPCO · Gyeonggi-do
Ansan OUR Data Centre
Fine & Partners Asset Management · Sinwon-ro 91beon-gil 79, Danwon-gu, Ansan, Gyeonggi-do
Under constructionchanged 2026-10-15
7.6 MWrequested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 2 sources
- Market
- South Korea · Asia
- Grid
- KEPCO · KEPCO
- Place
- Sinwon-ro 91beon-gil 79, Danwon-gu, Ansan, Gyeonggi-do
- Network
- —
- Announced
- 2026-10-15
- Construction started
- 2026-10-12
- First reported by
- fnnews.com · under construction
- Dates it gives
- construction start 2026-10-12
completion target 2027-10
Who is on it
- Builder
- CJ대한통운 건설부문 · fnnews.com
- Tenant
- 세종네트웍스 · fnnews.com
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
- ≤ 2026-10-15date: document dateon or before
-
2026-10-12
stageUnder construction1 source
- fnnews.com press
'안산 OUR 데이터센터' 개발사업은 총사업비 1390억원의 조달을 끝내고 지난 12일 착공했다.
- fnnews.com press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.