The Hook Lab / Tracker / Oceania / Australia / AirTrunk SYD3 Updated 2026-11-25
Tracker · Australia · NEM · NSW

AirTrunk SYD3

AirTrunk · Huntingwood, NSW

Planning approvedchanged 2023-09-15
—requested
—offered
—energised
55 mowaiting since first filing
highconfidence · 3 sources
Market
Australia · Oceania
Grid
NEM · National Electricity Market
Place
Huntingwood, NSW
Network
—
Announced
2022-10-25
Planning lodged
2022-04-26
Planning approved
2023-09-15
Planning lodged → approved
17 mo
First reported by
NSW planning portal · under construction
Dates it gives
Land bought 2021
320 MW plans filed 2021-11
SSD-41589232 approved 2023-09-15 (400 MW total)
A$4.25bn green loan 2026-10-28
expanded build due mid-2028

Timeline

2022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2023-09-15
    stagePlanning approvedconfirmed
  2. ≤ 2022-10-25date: document dateon or before
    stageAnnouncedconfirmed
    • announcements.asx.com.au primary
      AirTrunk also announced plans to expand into a third Sydney data centre with 320MW capacity and a second Tokyo data centre with 110MW capacity, creating total platform capacity of 1.2GW.
  3. 2022-04-26
    stagePlanning lodgedconfirmed

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.